Level 2 EV Charger Installation with Permit in Charlotte, NC completed by Touchstone Electric
Completed Project

Level 2 EV Charger Installation with Permit in Charlotte, NC

EV Charging completed by Touchstone Electric in Charlotte.

CharlotteCompleted: October 2, 2025
Service TypeEV Charging
Project TypeLevel 2 EV Charger Installation
Work StandardCode compliant
Performed ByLicensed electricians
Call 855-502-2244

Level 2 EV Charger Installation in Charlotte, NC

Touchstone Electric’s Charlotte branch completed a permitted Level 2 EV charger installation in Charlotte, NC for Duke Energy - Allumia. Led by our technician, Viktor Opalko, this project delivered a dedicated 240V circuit and clean, code-compliant routing to support reliable home charging. Completed on October 2, 2025, the installation was designed to align with Duke Energy’s rebate requirements for added customer value.

Project scope and highlights

  • Installed a dedicated 240V, 60-amp circuit for a Level 2 EV charger.
  • Added a new 60A breaker in the service panel for safe, dedicated power.
  • Ran #6 SEU (3-wire) feeder to meet the amperage and distance needs.
  • Routed wiring in 1-inch PVC conduit with proper fittings and supports for a neat, durable path.
  • Secured a permit and coordinated inspection to support utility rebate eligibility.
  • Connected the customer-supplied EV charging equipment per manufacturer specifications.
  • Performed function checks and labeling for user clarity and safety.

This setup provides faster charging, dependable performance, and a professional finish that blends with the home’s layout.

Permit-first installation for Duke Energy rebate eligibility

Many utility rebates require proof of a permitted, inspected installation. Our team handled the permitting from start to finish, ensuring the work could be documented for the Duke Energy EV charger rebate. From panel updates to conduit routing, all steps were completed with the rebate guidelines and local codes in mind.

If you’re planning a charger in Charlotte, we’ll guide you through what’s needed to qualify, including proper circuit sizing, inspection scheduling, and final documentation.

Materials and methods used

  • 60A breaker dedicated to the EV charging circuit.
  • #6 SEU cable sized for the load and run length.
  • 1-inch PVC conduit with connectors, LBs, and secure mounting for a clean, protected installation.
  • Terminations torqued to spec and labeled per best practices.

Every connection and component was installed to meet or exceed current electrical standards for EV charging (NEC Article 625), supporting safe operation and long service life.

Why Charlotte homeowners choose Touchstone Electric

  • Local expertise: Completed by our Charlotte team based out of our Matthews branch, with deep knowledge of area codes and inspection processes.
  • End-to-end service: We verify panel capacity, size the circuit, pull permits, and complete a tidy, warrantable installation.
  • Rebate-ready work: Installations aligned with Duke Energy program requirements help customers pursue available incentives.
  • Future-ready capacity: A 60A circuit supports many popular Level 2 chargers for faster, more flexible charging.

Customer feedback

Duke Energy - Allumia praised our team with a review for this Charlotte project. See their feedback here: Read the Google review.

Plan your Level 2 charger installation in Charlotte

From single-family homes to multifamily common areas, Touchstone Electric provides safe, efficient Level 2 EV charger installations across Charlotte, NC. If you’re upgrading to faster charging, our Matthews-based Charlotte team can deliver a clean installation, proper permitting, and guidance on rebate eligibility—start to finish.

Ready to charge faster at home? Contact our Charlotte team to schedule your on-site assessment and get a rebate-ready Level 2 EV charger installation.